Post: 2: This post is post the answer to the RFI question 6. 6. The expected approximate lead time for the new pump is 27 weeks (after submittal approval). Please confirm the NTP will not be issued by the Government until after the pump is delivered to the Contractor and onsite. Once we receive the manufacture delay letter, a suspension of work would be issued. It will also be posted in the attachment section as RFI Answers 7152025R The point of contact information has been updated fron Jalien Bankhead to Bryon Cassidy. ________________________________________________________________________________________________________ Post 1 .... Read More |
||