Kimball Creek Culvert Replacement FR-304

Posted Date: Jan 29, 2026
Feb 04, 2026
Awarded Date: No Awarded Date
SetAside Type
Solicitation ID Solicitation Title Solicitation Office
12445526R0001 Kimball Creek Culvert Replacement FR-304
Synopsis

Additional Q&A's attached. 

The purpose of this update is to clarify the period of performance.  The period of performance is 6/1/2026-9/30/2026 with instream work done between 7/1/2026-9/15/2026.  There is a revised drawing taking place of MN ERFO FS SPERI909 2022 and a geo tech report attached. 

Questions and answer document has been attached. 

The purpose of this update is to add additional attachments for the below:

Sheet R07 and R08 (aka bridge plan sheet 7 and 8 of 10) were missing the dimensions for the reinforcing steel. 

Second, there is .... Read More

Office Location Agency Name Solicitation Base Posting Type
FOREST SERVICE Combined Synopsis/Solicitation
SetAside Type
Solicitation ID Solicitation Title Solicitation Office
12445526R0001 Kimball Creek Culvert Replacement FR-304
Synopsis

Questions and answer document has been attached. 

The purpose of this update is to add additional attachments for the below:

Sheet R07 and R08 (aka bridge plan sheet 7 and 8 of 10) were missing the dimensions for the reinforcing steel. 

Second, there is a change to sheet S02 “Temporary Diversion Channels”.  There was a question regarding Note 1 on Temporary Diversion Channel drawing S-02.  Note 1 has been revised to explain that the temporary diversion details provided are proposed details and the contractor is responsible for the design of the diversion channel/culvert.  A table .... Read More

Office Location Agency Name Solicitation Base Posting Type
FOREST SERVICE Combined Synopsis/Solicitation
SetAside Type
Solicitation ID Solicitation Title Solicitation Office
12445526R0001 Kimball Creek Culvert Replacement FR-304
Synopsis

The purpose of this update is to add additional attachments for the below:

Sheet R07 and R08 (aka bridge plan sheet 7 and 8 of 10) were missing the dimensions for the reinforcing steel. 

Second, there is a change to sheet S02 “Temporary Diversion Channels”.  There was a question regarding Note 1 on Temporary Diversion Channel drawing S-02.  Note 1 has been revised to explain that the temporary diversion details provided are proposed details and the contractor is responsible for the design of the diversion channel/culvert.  A table of peak flows has also been added to drawing S-02 .... Read More